As WTC Dispute Heads for Phase II, Silverstein Says Setback Will Affect Rebuilding
NEW YORK //BestWire// - Larry Silverstein and other leaseholders of the World Trade Center suffered a $2 billion setback when a federal jury last week sided with most of the insurers who resisted Silverstein's claim that they had bound to property coverage under a form that might define the twin towers' destruction as two events, rather than one.
Yet another courtroom encounter looms, however, and for Silverstein, another $1 billion-plus change is on the line.
The 10-week trial (plus two weeks of jury deliberations) just ended before Judge Michael B. Mukasey in U.S. District Court for the Southern District of New York-Phase I-asked a jury to judge which of the 12 plaintiff insurers had committed to the form issued by Willis Group Holdings Inc. (NYSE:WSH), known as WilProp 2000. A previous federal court ruling had already determined that WilProp defines the destruction of the World Trade Center as a single event. That jury found that nine of the 12 insurers-with a total per-occurrence exposure of $1.93 billion-did bind under WilProp.
The leaseholders of the World Trade Center-Silverstein Properties and Westfield Properties-could have collected double that amount from the insurers if they had been bound to a form that interprets the destruction as two events. Silverstein argued in the trial-Phase I of an anticipated three phases in the insurance dispute-that the insurers switched from WilProp to a form issued by Travelers Insurance Co. (NYSE:TAPa). How the Travelers form interprets the events of Sept. 11, 2001, has yet to be determined in court.
All insurers and reinsurers involved in the World Trade Center property insurance program who were found to have bound to coverage under a form other than that used by Willis will face another jury, which will decide what form they bound under, and what that form says about whether the destruction of the twin towers was one event or two.
That is what will happen in Phase II. The three insurers found not to have been bound by WilProp in Phase I-Royal Indemnity, Zurich America and Twin City Fire-will join seven other insurers who did not participate in the Phase I trial-all with an aggregate $1.13 billion in per-occurrence exposure-in the Phase II trial.
Thus, Silverstein and his partners, who lost $1.93 billion of what they defined as possible recoverables in the Phase I trial, can lose as much as $1.13 billion more if Phase II goes against them.
The insurers, of course, don't see it that way. Jacques E. Dubois, chairman of Swiss Re America Holding Inc., said after the Phase I verdict that Swiss Re had always considered the total $3.55 billion payout-from all insurers put together-as the only possible maximum exposure under terms agreed to prior to Sept. 11. Silverstein insisted the insurers owed an aggregate $7 billion under a two-occurrence interpretation.
The Phase II trial will hinge on interpreting the wording of the Travelers form, and whether it says something different than WilProp about the definition of an occurrence, said Ralph Tortorella III, senior partner/resident director and member of the catastrophic insurance practice group in the New York office of the national law firm Ropers Majeski Kohn & Bentley. That task of interpretation is similar to what occurred when one of the original insurers in the dispute, St. Paul Fire & Marine Insurance Co., asked a federal judge for a summary judgment based on the language used in its binder, Tortorella said.
Judge John S. Martin Jr. of New York's Southern District reviewed the binding agreement, and ruled that St. Paul bound under a form that defined the twin towers' destruction as a single event (BestWire, Sept. 25, 2002). St. Paul, with $30 million in per-occurrence exposure, was off the hook for double that amount. "That effort at interpretation might be similar to what will happen in Phase II," Tortorella said.
In the 2002 ruling, Martin rejected the leaseholders' argument that there was more than one reasonable way to interpret the clause in the WilProp form that defined "occurrence," setting the stage for a 2003 decision by the U.S. Court of Appeals for the 2nd Circuit to uphold a finding that WilProp defined the World Trade Center's destruction as a single occurrence.
Andrew J. Barile, president and chief executive officer of insurance and reinsurance consultancy Andrew Barile Consulting Corp. Inc., said the court will need to hear from people with expertise in insurance and reinsurance contract language to pin down the concept of "occurrence" in a binding document. "Years ago, we used to sell second-occurrence reinsurance coverage for catastrophes such as earthquakes," he said. "Whether or not you were willing to take on a multiple-occurrence risk was clearly spelled out."
Barile speculated that, in the World Trade Center case, too many coverage assumptions might have been stuffed into one binding document, creating vague language open to interpretation in a courtroom.
After the Phase I jury had reached its final verdict on the lead insurer, Swiss Reinsurance Co., Mukasey tentatively set August as a likely time frame for the start of Phase II, pending requests from attorneys for the insurers and leaseholders involved.
The legal loss in Phase I was seen by some New York media commentators as a blow to Silverstein's ambition to be at the center of a rebuilding plan at Ground Zero, though the developer insists he will forge ahead with development plans that include a 1,776-foot "Freedom Tower" and a complex of five buildings. Estimated cost of the project is $9 billion.
But Silverstein came out swinging after his courtroom setback, releasing a statement following the verdicts in which he said he was committed to forging ahead with the rebuilding project. He did not say whether any legal setbacks in his fight with the insurers would affect his plans.
Bud Perrone, a spokesman for Silverstein, said Silverstein plans to go ahead with development of the new building complex no matter the outcomes of the various insurance trials. "As far as Larry is concerned, there is no impact on the rebuilding plans from the trial outcome," he said.
Perrone added that it is too soon for Silverstein to decide whether to appeal the outcome of the trial.
In a May 5 speech to the Association for a Better New York., Gov. George E. Pataki said the "rebuilding timeline is on track" for the redevelopment of lower Manhattan, including a planned July 4 groundbreaking for the Freedom Tower. According to the Lower Manhattan Development Corp., the groundbreaking is three months ahead of schedule.
Pataki also announced that the Deutsche Bank building at 130 Liberty St., which was heavily damaged when the World Trade Center collapsed, will be demolished beginning in the fall. The building, also known as One Bankers Trust Plaza, was damaged by falling debris from the adjacent two World Trade Center towers destroyed in the Sept. 11 terrorist attack.
Deutsche Bank had its own legal dispute, with insurers of the building, over payment related to the demolition. The bank argued that it could not proceed with an estimated $230 million demolition job, which would make the 40-story, 565-foot tower the second tallest building in the world ever to be razed, unless they knew the insurers would pay for it (BestWire, Sept. 4, 2003). The insurers balked at paying until proof was offered that the building could not be salvaged.
About a year ago, the bank settled with two insurers-Chubb Corp. and Zurich North America-which provided half of the structure's $1.05 billion coverage. Last August, Deutsche Bank filed a lawsuit in New York state Superior Court against the other insurers, Allianz Insurance Co., a unit of Germany's Allianz AG Holding, and two units of France's Axa-Axa Corporate Solutions Insurance Co. and Axa Global Risks US Insurance Co. The bank is seeking a declaratory judgment against those insurers, forcing them to pay for the demolition.
In his speech, Pataki referred to Silverstein briefly, as he listed the names of developers, architects and other professionals involved in the rebuilding effort.. The governor's only reference to litigation came toward the end of his speech: "We will not be hindered by court battles or dissuaded by naysayers," he said of the rebuilding effort.
Silverstein Properties is already building a 750-foot tower on the site, known as 7 World Trade Center. The building will have 1.7 million square feet of office space on 52 floors when finished. Silverstein expects construction to be completed by the end of 2005. All five of the planned towers in the new complex will provide a total of about 10 million square feet of office space.
The Lower Manhattan Development Corp. is a joint city-state corporation established after Sept. 11, 2001, to help plan and coordinate the rebuilding of lower Manhattan, defined as everything south of Houston Street. Half of the LMDC's 16-member board is appointed by the governor, half by the mayor of New York City.
Tortorella said the speech by Pataki-coming just after the trial-in addition to Silverstein's comments, suggest funding is available for the rebuilding effort, litigation notwithstanding. "The indications from Pataki and Silverstein are that it is going to be built," he said. There must be other sources of funding."
The Port Authority of New York and New Jersey, owner of the World Trade Center site from which Silverstein and Westfield obtained a 99-year lease, also appears confident the rebuilding will move forward as planned-with Silverstein's participation. Port Authority spokesman Pasquale DiFulco said Executive Director Joseph J. Seymour had expressed disappointment with the verdicts in the Phase I trial, but emphasized that Silverstein Properties had "publicly committed" to building the Freedom Tower.
"In addition, federal funding to build the World Trade Center transportation hub...has already been set aside, and the World Trade Center Memorial, which is the heart of the rebuilt World Trade Center site, will move forward," said Seymour in a statement. "In addition to its work on the Freedom Tower, Silverstein Properties must work with us on the critical infrastructure improvements necessary to support security, pedestrian and vehicular elements that will make the full World Trade Center site plan a success."
(By David Pilla, senior associate editor, BestWeek: David.Pilla@ambest.com)